Inspection and monitoring of built structures at TshoRolpa Glacier Lake Site and preparation of proposal on preservation activities necessary at the site
consulting_placeholder
Play Video

Aim of the study

RECHAM Consult (Pvt.) Ltd, Putalisadak, Kathmandu has taken the responsibility of Suspended Sediment Sampling and Laboratory Analyses, Staff Gauge Installation, and Discharge Measurement of the Budhigandaki Hydroelectric Project (341 MW).

Measurement works were carried out by following standard practices in hydrology and the DHM. Area-Velocity Method was applied to measure the discharges of the River. Sediment sampling of suspended sediment by the depth integration method, the adopted procedures of suspend sediment measurement.

Members involved

Suresh Marahatta

Senior Hydrologist/Team Leader

Nabaraj Dhakal

Hydrologist

Prabesh Dhungana

Hydrologist